Downtime cost calculator and machine hour rate

Enter your machine’s numbers to get its hourly rate, with and without the operator. Then see what every hour, and every minute, of downtime costs you.

Machine hour rate

$
Purchase price, installed.
$
What it is worth at the end of its useful life (resale or scrap).
years
h/yr
E.g. 250 days × 2 shifts of 8 h = 4,000 h.
%/yr
What the money would earn elsewhere. Applied to the average capital: (price + residual) ÷ 2.
$/yr
$/h
kW
%
How much of the rated power the machine draws, on average, while it runs.
$/kWh
ft²
$/ft²/mo
$/h
Wage plus benefits and payroll taxes, per hour worked. Shown separately in the result.

Cost of downtime

units/h
$/unit
Selling price minus materials and other variable costs. Leave labor in: it is counted below.
people
$/h
Wage plus benefits and payroll taxes, per hour.
$/h
Accounting view. Leave at zero when you use contribution margin, so nothing is counted twice.
h/mo

Result

Machine hour rate

$15.48per machine hour, without operator
With operator
$45.48/h

What makes up the hourly rate

  • Depreciation$5.00/h
  • Cost of capital$3.00/h
  • Maintenance$2.50/h
  • Energy$1.08/h
  • Floor space$0.90/h
  • Tooling and consumables$3.00/h

Cost of downtime

$300.00per hour of downtime
Per minute
$5.00
Per month
$3,600
Per year
$43,200
  • Lost margin$240.00/h
  • Idle labor$60.00/h
  • Fixed cost$0.00/h

12 downtime hours a month cost $3,600 a month.

How to calculate the machine hour rate

The machine hour rate takes everything a machine costs in a year and divides it by the hours it actually runs. Some costs are already hourly (energy, consumables) and go straight in.

Machine hour rate = depreciation + capital + maintenance + energy + floor space + consumables (all per hour)

Item Formula (per hour)
Depreciation (machine price − residual value) ÷ (useful life in years × hours per year)
Cost of capital (price + residual) ÷ 2 × interest rate ÷ hours per year
Maintenance maintenance per year ÷ hours per year
Energy rated power (kW) × load factor × electricity rate ($/kWh)
Floor space area (ft²) × cost per ft² per month × 12 ÷ hours per year
Consumables tooling, inserts, coolant and so on, already in $/h

The cost of capital is what the money sunk in the machine would earn elsewhere. The rate applies to the average invested capital, (price + residual) ÷ 2, because the machine loses value over its life: it starts at the purchase price and ends at the residual value.

The operator stays out of the main total. The calculator shows the rate without and with the operator (wage plus benefits and payroll taxes per hour), because one operator may run several machines and every shop quotes that differently.

How to calculate the cost of downtime

An hour of downtime costs what you fail to earn plus what you pay for nothing:

Cost per downtime hour = lost margin + idle labor + fixed cost (optional)

Lost margin = units per hour × contribution margin per unit

Idle labor = people idled × cost per person per hour

Lost margin only applies when the output is gone for good: the customer bought elsewhere, the order slipped and was cancelled, or the line already runs flat out. If the lost output is made up with overtime, no sale is lost. The cost becomes the overtime premium (people × hourly cost × premium, say 50%), on top of the labor that stood idle. Pick the case in the “Output lost during the stop” field.

Then multiply:

Cost per month = cost per downtime hour × downtime hours per month

Cost per minute = cost per downtime hour ÷ 60

Worked example

The values preloaded in the calculator describe a CNC lathe running two shifts.

Machine hour rate. A $250,000 machine with a $50,000 residual value, a 10 year life and 4,000 hours a year (250 days × 16 h):

  1. Depreciation = (250,000 − 50,000) ÷ (10 × 4,000) = $5.00/h
  2. Average capital = (250,000 + 50,000) ÷ 2 = $150,000. Cost of capital = 150,000 × 8% ÷ 4,000 = $3.00/h
  3. Maintenance = 10,000 ÷ 4,000 = $2.50/h
  4. Energy = 15 kW × 60% × $0.12 = $1.08/h
  5. Floor space = 200 ft² × $1.50 × 12 ÷ 4,000 = $0.90/h
  6. Tooling and consumables = $3.00/h

Machine hour rate = 5.00 + 3.00 + 2.50 + 1.08 + 0.90 + 3.00 = $15.48 per hour without the operator. With an operator at $30/h, $45.48 per hour.

Cost of downtime. The lathe makes 40 units an hour at a contribution margin of $6 each, and 2 people stand idle when it stops, at $30/h each:

  1. Lost margin = 40 × 6 = $240/h
  2. Idle labor = 2 × 30 = $60/h
  3. Cost per downtime hour = 240 + 60 = $300/h, or $5.00 per minute
  4. With 12 downtime hours a month: 300 × 12 = $3,600 a month and $43,200 a year

If the output were made up with overtime at a 50% premium, the cost would drop to 2 × 30 × 50% + 60 = $90 per downtime hour. Still money, but far less than a lost sale.

How to read the result

  • The machine hour rate is for quoting parts (machine time × hourly rate) and comparing processes: CNC or manual, make or buy. Look at which item weighs most: on an expensive machine depreciation and capital dominate, so every extra hour of use per year lowers the rate.
  • The downtime cost tells you what each minute saved is worth. At $300 per hour, a $1,000 spare part on the shelf pays for itself the first time it prevents a 4 hour breakdown.
  • Combine it with the MTBF and MTTR calculator: downtime hours per month = failures × MTTR. Cutting MTTR by 1 hour with 6 failures a month is worth 6 × 300 = $1,800 a month in the example.
  • Downtime also drags down availability and OEE, and takes capacity away from the line: see how much with the production capacity calculator.

Common mistakes

  • Dividing by all 8,760 hours in a year. The machine hour rate uses the hours the machine actually runs. On one shift that is about 2,000 hours, and the hourly rate doubles.
  • Using revenue instead of margin. A stopped machine does not use material, so only the contribution margin is lost.
  • Counting lost margin when the output is recovered. If overtime makes up the parts, no sale was lost. The cost is the overtime premium.
  • Adding fixed cost on top of lost margin. Contribution margin is the money that would have paid the fixed costs, so adding both counts the same dollars twice. Use the fixed cost field only for the accounting view, with the margin at zero.
  • Forgetting the people around the machine. On a line, one stopped machine starves the stations after it and blocks the ones before. Count everyone left waiting.

Frequently asked questions

How do you calculate the cost of downtime per hour?

Add up, for one hour stopped, the contribution margin of the output you will not make up (units per hour × margin per unit), the labor paid to wait (people × hourly cost) and, if you want the accounting view, unabsorbed fixed cost. Multiply by downtime hours per month for the monthly cost.

What is a machine hour rate?

It is what one hour of a machine’s work costs: depreciation, the cost of the capital tied up in it, maintenance, energy, floor space and consumables, divided by the hours it actually runs in a year. It is used to quote parts and compare processes.

What is included in machine downtime cost?

Lost contribution margin on output that cannot be recovered, idle labor, and the cost of making up output when it is recovered (usually the overtime premium). Repair labor and spare parts are maintenance costs, so track them on the work order rather than in the hourly downtime rate.

Should I use revenue or margin for lost production?

Contribution margin: selling price minus materials and other variable costs. When a machine stops you lose the sale, but you also do not spend the material. Using full revenue overstates the cost of downtime.

What if we make up the lost output with overtime?

Then no sale is lost, so do not count the margin. The cost becomes the overtime premium (people × hourly cost × premium, e.g. 50%) on top of the idle labor during the stop. Pick that case in the calculator and it switches the formula.

What is the average cost of downtime in manufacturing?

There is no useful average: it ranges from a few dollars a minute on a standalone machine to very large sums on a bottleneck in a continuous process. Industry surveys quote big numbers, but your own figure, from your output rate and margin, is the one that justifies a spare part or a maintenance hire.