How SMED works
Shigeo Shingo developed SMED through the 1950s and 1960s at plants such as Mazda and Toyota, and wrote it up in A Revolution in Manufacturing: The SMED System (1985). The method has four steps:
- Watch the changeover as it is. Film and time every step, from the last good part to the first good part.
- Separate internal and external setup. Internal needs the machine stopped. External can happen while it runs.
- Convert internal to external. Stage the tools, preheat the dies, preset the fixtures before the machine stops.
- Streamline both. Quick clamps instead of bolts, standard heights that need no adjustment, two people working in parallel, no trial parts.
Steps 2 and 3 alone, with no spending on equipment, often cut setup by 30% to 50%.
The math
Hours freed per month = (current setup − new setup) × changeovers per month
Savings per month = hours freed × cost of an hour of stopped line
Extra capacity = hours freed × output per hour
If you do not know the hourly cost of a stopped line yet, work it out with the downtime cost calculator.
Worked example
The calculator starts with an injection molding machine: setup of 45 min, target 15 min, 3 changeovers a day, 22 days a month, a stopped hour costing $150 and 120 units per hour.
- Changeovers per month: 3 × 22 = 66
- Saved per changeover: 45 − 15 = 30 min (a 67% reduction)
- Hours freed: 66 × 0.5 h = 33 h per month, or 396 h per year
- Money: 33 × $150 = $4,950 per month, or $59,400 per year
- Extra capacity: 33 × 120 = 3,960 units per month, or 47,520 per year
Smaller lots in the same setup time
The biggest SMED gain is often not the freed hour. Today the machine spends 66 × 45 min = 49.5 h a month on setup. At 15 minutes a changeover, those same 49.5 h fit 198 changeovers instead of 66: three times as many, with lots three times smaller. Smaller lots mean less inventory sitting around, faster response to customers and shorter lead time, and Little’s law shows why.
Common mistakes
- Timing only the tool swap. Setup runs until the first good part, adjustments and trials included.
- Counting money on a machine with spare capacity. If it is not the bottleneck, a freed hour does not become a sale. The gain is in smaller lots and less inventory.
- Buying equipment before separating internal and external. Most of the gain comes from organization.
- Not standardizing. Without a written procedure for the new changeover, the time creeps back within weeks.
Freed hours on a bottleneck raise availability and OEE. To see what the line can make with the time you gain, use the production capacity calculator.