Line balancing calculator and Yamazumi chart

Enter the demand and paste the line’s operations with their times per station. The calculator draws the Yamazumi chart, shows the efficiency, the bottleneck and how many operators are enough, and suggests a new grouping within takt.

Demand and operations

min
Shift minus planned breaks. E.g. 480 − 30 = 450 min.
shifts
units/day
%
For the balancing suggestion: the most each station may carry, as a % of takt. 95% leaves some slack.
One operation per line, in process order: station; operation; seconds; type. Type: VA (value adding), NNVA (necessary non value adding) or NVA (waste). No type counts as VA. Paste straight from a spreadsheet.

Result

61.8%line balance efficiency

5 stations, 204 s of work per unit. Takt 60 s, line cycle 66 s (bottleneck: S3).

The line cannot keep up with takt

Over takt: S3. The line makes 818 units per day, 82 short.

Takt time
60 s
Line cycle (bottleneck)
66 s
Minimum operators
4
Balance delay
38.2%
Idle time per cycle
126 s
Capacity per day
818 units
Current Yamazumi chart
0255075100S1 · Pick up the base · NNVA: 5 sS1 · Mount the motor on the base · VA: 24 sS1 · Screw the motor · VA: 16 s45S1S2 · Fetch the fan blade from stock · NVA: 9 sS2 · Fit the fan blade · VA: 12 sS2 · Tighten the nut · VA: 10 sS2 · Check the clearance · NNVA: 7 s38S2S3 · Fit the rear guard · VA: 15 sS3 · Route the cable · VA: 18 sS3 · Wait for the screwdriver · NVA: 8 sS3 · Clip the cable · VA: 11 sS3 · Fit the front guard · VA: 14 s66S3S4 · Function test · NNVA: 20 sS4 · Apply the label · NNVA: 5 s25S4S5 · Walk to the pallet · NVA: 6 sS5 · Pack · VA: 16 sS5 · Close the box · VA: 8 s30S5Takt 60 s
  • Value adding (VA)144 s · 71%
  • Necessary, no value (NNVA)37 s · 18%
  • Waste (NVA)23 s · 11%

Load per station

StationVANNVANVATotal (s)% of takt
S140504575%
S222793863%
S3580866110%
S402502542%
S524063050%

Balancing suggestion

The same operations, in the same order, grouped into the fewest stations loaded up to 57 s (95% of takt). Result: 4 stations, 55 s cycle, 92.7% efficiency and 981 units per day.

Suggested Yamazumi chart
0255075100Station 1 · Pick up the base · NNVA: 5 sStation 1 · Mount the motor on the base · VA: 24 sStation 1 · Screw the motor · VA: 16 sStation 1 · Fetch the fan blade from stock · NVA: 9 s54Station 1Station 2 · Fit the fan blade · VA: 12 sStation 2 · Tighten the nut · VA: 10 sStation 2 · Check the clearance · NNVA: 7 sStation 2 · Fit the rear guard · VA: 15 s44Station 2Station 3 · Route the cable · VA: 18 sStation 3 · Wait for the screwdriver · NVA: 8 sStation 3 · Clip the cable · VA: 11 sStation 3 · Fit the front guard · VA: 14 s51Station 3Station 4 · Function test · NNVA: 20 sStation 4 · Apply the label · NNVA: 5 sStation 4 · Walk to the pallet · NVA: 6 sStation 4 · Pack · VA: 16 sStation 4 · Close the box · VA: 8 s55Station 4Takt 60 s
StationOperationsLoad (s)% of takt
Station 1Pick up the base, Mount the motor on the base, Screw the motor, Fetch the fan blade from stock5490%
Station 2Fit the fan blade, Tighten the nut, Check the clearance, Fit the rear guard4473%
Station 3Route the cable, Wait for the screwdriver, Clip the cable, Fit the front guard5185%
Station 4Function test, Apply the label, Walk to the pallet, Pack, Close the box5592%

How to calculate line balancing

Balancing a line answers three questions: what pace demand calls for, how much work goes into each unit, and how to split that work across stations so none of them falls behind the pace.

Takt = available time ÷ demand

Minimum operators = total work content ÷ takt (rounded up)

Balance efficiency = total work content ÷ (stations × bottleneck cycle)

Balance delay = 1 − efficiency

Term What it is
Takt the pace demand calls for. See the takt time calculator
Total work content every operation at every station, for one unit
Bottleneck cycle the time of the most loaded station. It sets the real pace of the line
Idle time per cycle stations × bottleneck cycle − total work: the seconds the whole line spends waiting on each unit

Task times come from a time study. Use the standard time, with rating and allowances, not the raw stopwatch average.

Worked example

The values loaded in the calculator are from a fan assembly line:

  • 450 min available per shift, 2 shifts: 54,000 seconds per day
  • Demand of 900 units per day
  • 17 operations across 5 stations, 204 seconds of work per unit

1. Takt. 54,000 ÷ 900 = 60 seconds per unit.

2. Station loads. S1 = 45 s, S2 = 38 s, S3 = 66 s, S4 = 25 s, S5 = 30 s. S3 is over takt: it is the bottleneck, and the line can only release one unit every 66 seconds.

3. Capacity. 54,000 ÷ 66 = 818 units per day, 82 short of demand.

4. Minimum operators. 204 ÷ 60 = 3.4, rounded up: 4 operators. The line has 5 and still falls short. The problem is not headcount, it is how the work is split.

5. Efficiency. 204 ÷ (5 × 66) = 204 ÷ 330 = 61.8%. Balance delay is 38.2%: on every unit the line spends 126 seconds waiting (330 − 204).

6. Rebalancing. With a target of 95% of takt (57 s per station), the operations are grouped in process order, filling each station as far as it goes:

Station Operations Load
Station 1 pick up the base, mount the motor, screw the motor, fetch the fan blade 54 s
Station 2 fit the blade, tighten the nut, check the clearance, fit the rear guard 44 s
Station 3 route the cable, wait for the screwdriver, clip the cable, fit the front guard 51 s
Station 4 test, label, walk to the pallet, pack, close the box 55 s

Result: 4 stations instead of 5, a 55 second cycle, efficiency of 204 ÷ (4 × 55) = 92.7% and capacity of 54,000 ÷ 55 = 981 units per day. The line now meets demand with one operator fewer.

How to read the Yamazumi chart

Each column is a station, and each block is a task colored by work type:

  • Value adding (VA): changes the product in a way the customer would pay for. Assembling, fastening, packing.
  • Necessary non value adding (NNVA): does not change the product but cannot be removed today. Tests, checks, picking up the part.
  • Waste (NVA): can be eliminated. Fetching material from far away, waiting for a tool, walking.

The red line is takt. A column above the line is a station holding up the whole line. Very uneven columns mean there is room to move tasks. And the orange blocks (waste) are the first to go: in the example, 23 seconds per unit (fetching the blade, waiting for the screwdriver, walking to the pallet) could become slack without hiring anyone.

How the suggestion works

The suggestion walks through the operations in the order you pasted them and fills each station up to the target. When the next operation does not fit, it opens a new station. It is the same logic as the GBO in TaktZen.

The default target is 95% of takt. Planning stations right at takt (100%) leaves no margin for small stops and operator variation, and many plants plan between 85% and 95%. An operation longer than the target gets a station of its own; the fix is then to split it or improve the method.

Treat the suggestion as a starting point. It does not know that two tasks share a tool, that a station sits on the other side of the line, or that a task is too heavy to repeat all shift. Check it with the people who work the line.

Common mistakes

  • Using raw stopwatch averages. Without rating and allowances, every station looks like it has more slack than it does.
  • Balancing right to takt. A station at 99% of takt falls behind the first time a screw drops.
  • Moving tasks out of sequence. You cannot pack before testing. The suggestion on this page keeps the pasted order.
  • Using takt instead of the bottleneck in the efficiency. Some textbooks compute work ÷ (stations × takt). That measures the line as it should be; with the bottleneck cycle you measure the line as it is.
  • Stopping at the balance. Check that the cycle covers demand with the production capacity calculator and track real losses with OEE.

Frequently asked questions

What is line balancing?

Line balancing is spreading the work across stations so each one carries about the same load and none exceeds takt time. A balanced line meets demand with the fewest operators and little waiting between stations.

How do you calculate line balancing?

Work out takt (available time ÷ demand), add up the time of every operation and divide by takt for the minimum number of stations, rounded up. Then group the operations in process order without letting any station go over takt, and check the efficiency: total work ÷ (stations × slowest station time).

How do you calculate line balance efficiency?

Efficiency = total work content ÷ (number of stations × bottleneck cycle time). With 204 seconds of work over 5 stations and a 66 second bottleneck, it is 204 ÷ 330 = 61.8%. The gap to 100% is the balance delay.

What is a Yamazumi chart?

A Yamazumi chart is a stacked bar chart with one column per station or operator, each column built from that station’s tasks and colored by work type (value adding, necessary non value adding, waste). A horizontal line marks takt. Yamazumi means "stack up" in Japanese.

How do you make a Yamazumi chart?

Time every task at each station, classify each one as value adding, necessary non value adding or waste, and stack the times into one column per station with a color per type. Draw the takt line across. Paste the tasks into this calculator and it draws the chart for you.

What is the minimum number of workstations?

Total work content divided by takt time, rounded up. 204 seconds of work at a 60 second takt gives 3.4, so at least 4 stations. Real lines often need one more, because tasks cannot be split to fill every station exactly.