Kanban calculator: number of cards

Enter daily demand, replenishment lead time, parts per container and a safety margin to see how many cards the loop needs and how much inventory it will hold.

Part data

parts/day
What the customer process uses per working day.
days
From the moment the card is pulled until the full container is back: queue, changeover, run and transport. In days (4 h in an 8 h day = 0.5).
parts
%
Parts per bin or box. Each card stands for one container. Allowance for swings in demand and replenishment. Start at 10% and cut it as the process settles.

Result

22kanban cards in the loop

480 × 2 × 1.10 ÷ 50 = 21.12, rounded up

Each card authorizes the upstream process to make one container of 50 parts.

Most inventory in the loop
1,100 parts
Coverage
2.3 days of demand
Without the safety factor
20 cards
Extra from rounding up
44 parts

How to calculate the number of kanban cards

The loop needs enough cards to cover what the line uses while an empty container travels, gets refilled and comes back. This is the formula from the Toyota Production System:

N = D × L × (1 + α) ÷ C, rounded up

Term Meaning
N number of kanban cards (one per container)
D average daily demand of the customer process
L replenishment lead time in days: from the card being pulled to the full container returning
α safety factor, for swings in demand and replenishment
C parts per container

The most inventory the loop can hold is N × C. Divided by daily demand, it becomes days of coverage.

Production kanban and supplier kanban

The same formula works for both. What changes is what you add up in the lead time:

  • Production kanban: the time the card waits on the board before it is scheduled, queue time, changeover, the time to run the lot and the move to the supermarket.
  • Supplier or withdrawal kanban: the pickup or ordering interval (if the truck comes every 2 days, a card can wait up to 2 days), the supplier lead time and transit.

If you have the time in hours, turn it into working days: 4 hours in an 8 hour day is 0.5 day.

Worked example

The values already in the calculator are for a part used on an assembly line:

  • Demand: 480 parts per day
  • Replenishment lead time: 2 days
  • Safety factor: 10%
  • Container: 50 parts per bin

The math:

  1. Usage during replenishment = 480 × 2 = 960 parts
  2. With safety = 960 × 1.10 = 1,056 parts
  3. Cards = 1,056 ÷ 50 = 21.12, rounded up: 22 cards
  4. Most inventory in the loop = 22 × 50 = 1,100 parts, or 1,100 ÷ 480 = 2.3 days of demand

Without the safety factor it would be 20 cards. Rounding up alone adds 44 parts to the loop, almost a full container.

Two bins: the simplest case

When the math gives 2 cards or fewer, the loop becomes a two-bin system: one bin in use at the station and a full one in reserve. When the first empties, it goes back for refilling and the operator switches to the second. The calculator never shows fewer than 2 cards, because with one there is nothing to use while the container is being refilled.

How to read the result

  • Too many cards means too much inventory in the loop. The levers are a shorter lead time (faster changeovers, more frequent pickups) and smaller containers. The safety factor is the last thing to touch.
  • Days of coverage tell you how long the line can run if replenishment stops. Compare it with how long a supply problem really takes to fix.
  • Daily demand is the same figure that sets the pace of the line. When demand changes, recalculate the kanban and the takt time together.
  • Inventory and lead time move together: by Little’s law, more parts in the loop at the same throughput means longer flow time.

For bought parts run on an order quantity and a reorder point instead of cards, use the safety stock and reorder point calculator and the EOQ calculator.

Common mistakes

  • Using only the run time as the lead time. The card also waits on the board, in the queue and in transit. Leaving those waits out starves the loop.
  • Rounding down. 21.12 cards is 22. With 21 the loop has no margin beyond the safety factor.
  • Never revisiting the card count. Demand, changeovers and pickup frequency change. Review the cards whenever demand shifts, or at least monthly.
  • Using the safety factor to hide problems. If replenishment is always late, raising α only hides the cause. Kanban is there to show where flow gets stuck.

Sources

  • Monden, Yasuhiro. Toyota Production System: An Integrated Approach to Just-In-Time. 4th ed. CRC Press, 2011. Chapter on determining the number of kanbans.
  • Ohno, Taiichi. Toyota Production System: Beyond Large-Scale Production. Productivity Press, 1988.

Frequently asked questions

How do you calculate the number of kanban cards?

Multiply daily demand by the replenishment lead time in days, add the safety factor and divide by the container quantity. Always round up. With 480 parts a day, a 2 day lead time, 10% safety and bins of 50: 480 × 2 × 1.10 ÷ 50 = 21.12, so 22 cards.

What is the kanban formula?

The formula Toyota uses is N = D × L × (1 + α) ÷ C, where D is demand per period, L the replenishment lead time in the same period, α the safety factor and C the container quantity. Each card stands for one container.

What goes into the kanban lead time?

All the time from the card leaving the container until the full container is back at the point of use: the card waiting on the board, queue time, changeover, run time and transport. For a supplier kanban, add the pickup or ordering interval, the supplier lead time and transit.

What safety factor should I use?

Teams often start at 10% to 20% and cut it as the process settles. The safety factor covers swings in demand and replenishment. If it has to be large, the real problem is process stability, and that is where improvement should go.

What is the difference between a production kanban and a withdrawal kanban?

A production kanban tells the upstream process to make one container. A withdrawal (or supplier) kanban tells someone to pick one container from the supermarket or order it from the supplier. The card count math is the same; only what goes into the lead time changes.

What is a two-bin system?

The simplest kanban: two bins of the same part, one in use and one full in reserve. When the first empties, the empty bin itself is the signal to refill it. It suits cheap parts with steady use, such as fasteners and consumables.