Enter the machine’s cycle, your shifts and planned losses to get design, available, effective and actual capacity, utilization and efficiency, and how many machines or shifts demand calls for.

Machine or line

s/unit
The fastest cycle the machine runs, per unit. Use a measured time study cycle, not the average.
mach.

Period and shifts

days
days
shifts
h

Planned losses

min/shift
h/mach.
h/mach.
Changeovers and maintenance in hours per machine, summed over the period.
units
Good units made by all machines in the period.
units

Result

45,440units of effective capacity in the period

From design to actual capacity

Design115,200 units
720 h per machine: 24 h × 30 days
Available56,320 units
352 h per machine: days × shifts × hours
Effective45,440 units
284 h per machine: available minus 68 planned hours
Actual36,000 units
79.2% of effective
Utilization (actual ÷ design)31.3%
Efficiency (actual ÷ effective)79.2%

To meet a demand of 45,000 units

Machines needed
3
on the same shifts
Shifts per day needed
3
with the same machines

At 100% efficiency, 2 machine(s) would do. The gap is what unplanned losses cost you.

How to calculate production capacity

Every capacity figure is time × rate. The rate is the machine’s output per hour at its ideal cycle. What changes from one stage to the next is the time you count:

Output per hour = 3,600 ÷ ideal cycle time (s), or the machine’s rated output

Capacity = hours × output per hour × number of machines

Capacity Hours per machine in the period What it shows
Design calendar days × 24 h the ceiling: the machine running nonstop, every day
Available working days × shifts × hours per shift what fits in your scheduled time
Effective available − planned losses (breaks, changeovers, planned maintenance) what you can make if everything goes to plan
Actual (the output you enter) what really came out

With actual output you get the two ratios defined by Slack, Chambers and Johnston (Operations Management):

Utilization = actual output ÷ design capacity

Efficiency = actual output ÷ effective capacity

Some textbooks and plants use the words differently (for example, utilization against available rather than design capacity). Before comparing numbers with another site, check which definition each one uses.

How many machines or shifts demand calls for

Enter the period’s demand and the calculator shows:

Machines needed = round up (demand ÷ actual output per machine)

Shifts needed = round up (demand ÷ actual output per shift)

It uses actual output, not effective capacity, because actual output is what you can count on today. It also shows how many machines would do at 100% efficiency: the gap is what unplanned losses cost you in equipment.

Worked example

The values preloaded in the calculator describe 2 identical machines with a 45 second ideal cycle, in a 30 day month with 22 working days on 2 shifts of 8 hours:

  1. Output per hour = 3,600 ÷ 45 = 80 units/h per machine, 160 for both
  2. Design = 30 × 24 = 720 h × 160 = 115,200 units
  3. Available = 22 × 2 × 8 = 352 h × 160 = 56,320 units
  4. Planned losses per machine: 1 h of breaks per shift (22 × 2 × 1 = 44 h), 16 h of changeovers and 8 h of planned maintenance = 68 h
  5. Effective = (352 − 68) = 284 h × 160 = 45,440 units
  6. Actual = 36,000 units
  7. Utilization = 36,000 ÷ 115,200 = 31.3%
  8. Efficiency = 36,000 ÷ 45,440 = 79.2%

For a demand of 45,000 units in the month: each machine made 18,000, so you need 45,000 ÷ 18,000 = 2.5, that is 3 machines on the same 2 shifts. Or, with the 2 machines, 3 shifts (2.5 rounded up), which still fit in 24 hours. At 100% efficiency each machine would make 22,720 units and 2 machines would do.

How to read the result

  • Low utilization is almost always calendar time with no shift: weekends, a third shift that does not exist. That capacity is bought with people, not machines. In the example, 31% utilization says there is room to grow without new equipment.
  • Low efficiency is loss inside the shift that was not in the plan: breakdowns, minor stops, slow running and scrap. That is where the OEE calculator splits the losses apart, and the MTBF and MTTR calculator tackles breakdowns.
  • The gap between available and effective is planned losses. Long changeovers take hours from every machine, every month. Quick changeover (SMED) gives those hours back.
  • Before buying a machine, compare the two answers: if 100% efficiency would cover demand with the machines you have, attacking losses is cheaper. To put a price on each lost hour, use the downtime cost calculator.

Capacity efficiency and OEE

Both measure losses, but against different bases. OEE starts from planned production time and counts changeovers as an availability loss, because the machine could have been making parts. Capacity efficiency takes changeovers out of the base (they are a planned loss) and measures only what was lost outside the plan. So efficiency usually comes out higher than the same machine’s OEE. Use efficiency to plan capacity and OEE to go after losses, changeovers included.

Common mistakes

  • Using the average cycle instead of the ideal cycle. The average already has losses built in, so efficiency lands near 100% without the machine being any good. Measure the ideal cycle with a time study.
  • Adding up machines that work in series. On a line, capacity is the bottleneck’s, the slowest station. Work out each station and keep the lowest. To spread the work across stations, see line balancing and takt time.
  • Ignoring the product mix. With products on different cycles, use the average of the ideal cycles weighted by each one’s volume, or work in hours instead of units.
  • Planning on effective capacity. It assumes 100% efficiency. When you promise a date to a customer, use what the plant really delivers.

Frequently asked questions

How do you calculate production capacity?

Multiply time by output per hour. Design capacity uses 24 hours on every day of the period; available capacity uses only your scheduled shifts; effective capacity subtracts planned losses such as breaks, changeovers and preventive maintenance. Output per hour is 3,600 ÷ ideal cycle time in seconds.

How do you calculate the production capacity of a machine?

Take the ideal cycle time (say 45 seconds per unit), turn it into output per hour (3,600 ÷ 45 = 80 units/h) and multiply by the machine’s effective hours in the period: scheduled shift time minus breaks, changeovers and planned maintenance.

What is the difference between capacity utilization and efficiency?

In Slack, Chambers and Johnston’s definitions, utilization is actual output ÷ design capacity (how much of the ceiling you use) and efficiency is actual output ÷ effective capacity (how much of what was possible after planned losses you delivered).

What is design capacity?

The most a machine or plant could make running 24 hours a day, every day, at the ideal rate with no stops. Nobody runs like that, but it is the ceiling: it shows how far you could grow by adding shifts before buying equipment.

What is effective capacity?

Effective capacity is what you can make once planned losses are taken out of the scheduled time: breaks, changeovers, planned maintenance. It is the realistic target for a well run shift, and the base for the efficiency ratio.

Is capacity efficiency the same as OEE?

No. OEE counts changeovers as an availability loss, while capacity efficiency treats them as planned losses outside the base. That is why efficiency usually comes out higher than the OEE of the same machine.